Application of carpark system

  1. Apply following general recommendations detailed on Ultraflex application instructions, including temperature checks and substrate preparation recommendations.
  2. Priming ULTRAPRIME PRO. Open the 2 components and mix thorughly. Apply a layer of 150 – 200grs to all areas to be coated. Once Ultraprime is dry (in about 2 hours) it will be ready to be coated.
  3. Open Ultraflex drum and the QUICKCURE and mix thoroughly for 2 minutes before using. Apply the mixed Ultraflex on a wet on wet system, at a minimum coverage rate of 2kg per m2. Drying time will be approx. 2 hours depending on weather, fully cured in 24 hours.
    Coverage: A drum of Ultraflex will cover around 7 sqm depending on the surface.
  4. ULTRATOP WR: Mix the 2 components thoroughly and apply a 150grs layer of Ultratop WR topcoat once the Ultraflex is fully cured and no later than 48 hours after Ultraflex application. While wet, broadcast the aggregate onto the Ultratop WR and apply another layer of 150grs to encapsulate the aggregate.